|
|
|
|
 |
|
February, 2004
January, 2004
December, 2003
November, 2003
October, 2003
September, 2003
August, 2003
July,
2003
June,
2003
May, 2003
April,
2003
March,
2003
February, 2003
January, 2003
December, 2002
November, 2002
October, 2002
September, 2002
August, 2002
July, 2002
June, 2002
May, 2002
April, 2002
March, 2002
February, 2002
January, 2002
December,2001
November, 2001
October, 2001
September, 2001
August, 2001
July, 2001
June, 2001
May,
2001
April,2001
Briefs
March,
2001 Briefs
MichiganRailroads.com
News
Menu
Send In A News Tip
|
|
|
|
|
|
|
|
|
CSX Stanley Yard Closing April 1st...
CSX's Stanley Yard, a former Conrail, PC,
NYC facility, will all but close on April 1st. The jobs are being
transferred to Walbridge Yard.
Improvements to Lake States Railway
planned for this summer...
OTSEGO LAKE
TWP. - Twelve miles of railroad track between Gaylord and Grayling will
be improved this summer, with the help of about $2.5 million from the
Michigan State Transportation Commission, which recently granted a total
of $88 million for road and rail repairs. From rail mile post 103
near Grayling to mile post 116 in southern Otsego County, the track will
be getting new ties, stone ballast, and resurfacing. Work on the
repair project will start May 1, although crews are already working on
the rails, completing last year's repair project. The work will continue
through the summer, with a final completion date scheduled for the
middle of 2005. In spite of workers tearing up ties and
resurfacing the beds, Lake State Rail Company doesn't expect any major
inconveniences for trains traveling through the work site. "At the
most, there will be a 45-minute delay," said Wil Gamble, vice president
of operations for the rail company. "And workers will only block the
trains in one direction." Part of the repair process will include
disposing of old railroad ties. For the most part, ties are made of wood
treated with creosote, and can be chipped and burned. Infrequently, ties
were made of "green-treated" lumber, which contains copper, cyanide and
arsenic. "There's not much of that in the railroad industry, but if we
find some, we'll send it to a landfill," Gamble said. A separate
project to rebuild the rail crossing at Dickerson Road is scheduled to
begin this summer. From the Gaylord Herald-Times
Amtrak to reopen
three ticket offices...
LANSING, Mich., and CHICAGO – Under a new agreement between Amtrak and
the Michigan Department of Transportation (MDOT), ticket agents are
returning to the stations in Flint, East Lansing and Port Huron. The
agents will serve passengers traveling on Amtrak’s new
Blue Water service between
Port Huron and Chicago, which will begin April 25, 2004.
Passengers can now purchase tickets and get up-to-date information from
an Amtrak ticket agent at the station in Flint at 1407 South Dort
Highway and in East Lansing at 1240 South Harrison Road. The Port Huron
station, at 2223 16th Street, will also be staffed with a
ticket agent, effective April 23. The ticket agents are on duty in
Flint daily from 11:00 a.m. to 7:00 p.m. through April 24 and 5:30 a.m.
to 1:30 p.m., starting April 25. The ticket agents are on duty in East
Lansing daily from 10:30 to 6:30 p.m. through April 24 and 7:00 a.m. to
3:00 p.m., starting April 25. The Port Huron ticket office is
scheduled to open by April 23, with daily hours from 10:00 p.m. until
6:00 a.m.
Amtrak delay...
The eastbound Pere Marquette, Train
370(12MAR) with AMTK 516 reported ground relay problems several times
enroute from Chicago, finally was put into siding at Porter. Engine was
unable to move train from then on. Consist was coupled to
westbound International, Train 365, and returned to Chicago, where it
was terminated and passengers were to be put on buses. But Amtrak was
unable to get any buses, so AMTK 516 was replaced by AMTK 73 and train
departed again. Total delay, Train 370: 3 hr 57 min. Delay
to Train 365: 1 hr 05 min. From Mark Tomlonson.
Former Conrail Toledo branch to be
downgraded?
There is a rumor floading around
that effective April 1, CSX will discontinue through traffic on the
Toledo Branch (which leaves southbound from Stanley Yard towards Bowling
Green), leaving only locals to ply the route from Ridgeway to Stanley
Yard. Through traffic from Indianapolis/Columbus will be routed via
Marion and Fostoria to Walbridge, and Stanley Yard will eventually be
downgraded, or perhaps closed altogether. From
Brian Thom.
Unusual Amtrak Delay...
The westbound Lake Cities, Train
353(05MAR) with cab car AMTK 90215 and AMTK 31 in push mode stopped 18
miles west of Kalamazoo account ITCS problems (that's the dispatch/train
separation system). System malfunctioned, which takes traction power
offline. Crew unable to reset ITCS but were able to restore traction by
cutting out alerter and overspeed controls on the cab car. Per rules,
Conductor rode with engineer on head end when train continued.
Delay 1 hr 40min. From Mark Tomlonson.
Lake State Railway News...
Business is
picking up on the Mackinaw line to where they may need to increase
the three days per week service to five. Among this new traffic are
movements of particleboard south: LSRC to Central Michigan (Huron &
Eastern) @ Bay City, to T&SB @ Durand, to Ann Arbor @ Osmer and
finally Norfolk Southern @ Toledo. Strangely enough, everybody
makes money on the deal. CSX could have had the entire haul south
of Bay City but they priced themselves out of the market. [This is
also why Michigan corn from elevators on RailAmerica has been moving
to Canada by truck rather than by rail – CSX priced the through rate
too high.]
LSRC has received
a number of inquires concerning locating or expending business on
their lines – more on the Mackinaw line than on the Huron line. An
announcement was recently mad of an expansion of a metals recycler
in Gaylord that will require construction of a two mile-long spur.
The new siding constructed at MP 105 (between Frederic and Waters)
was put in for the purposes of serving potential future customers
and for storing track equipment. From the Bluewater
Chapter, NRHS.
On-time performance for Amtrak in
February...
Michigan Amtrak trains
were "On Time" in February 64.4% of the time. This means they
reached their destinations within 30 minutes of the schedule. (Airlines
use a 15 minute figure) This puts Michigan trains pretty much in the
middle in terms of Amtrak performance. The highest performing
trains in February were the Hiawathas between Chicago and Milwaukee with
a 94.9% on time performance. The lowest performing train was the
transcontinental Sunset Limited at 4% on time. From Mark
Tomlonson.
More News
Briefs from February... |